MD Law wins construction case at High Court

MD Law has acted in a construction case at the High Court winning a £140,000 award for its client.

BDP Construction Ltd had built a hospital for Cygnet Behavioural Health Ltd.

When BDP asked for the retention money (£170k), Cygnet refused and instead claimed £180k in liquidated damages for delay and defects. The dispute went to adjudication.

The adjudicator decided neither party had proved the correct liquidated damages rate, so awarded most of the retention to BDP. Cygnet refused to pay and argued in court that the adjudicator had no jurisdiction and breached the rules of natural justice because he should have chosen one of the two liquidated‑damages figures the parties had contended for.

The High Court rejected that argument with the head judge of the Technology & Construction Court enforcing the award, and ordering Cygnet to pay over £140k to BDP.

MD Law partner Neil Kelly, who worked with colleague Beth Bainbridge on the case, said: “The case highlighted the nuance between the parties agreeing a fact which an adjudicator cannot go behind on the one hand, and parties arguing a limited scope of outcomes for which the adjudicator is tasked with deciding, on the other.

“Our thanks goes to Adam Beaumont at Kings Chamber who worked with us on this successful outcome, which confirms our experience in contentious construction matters.”

The full details of the judgment:
In BDP Construction Limited v Cygnet Behavioural Health Limited [2026] EWHC 1796 (TCC) Mr Justice Constable granted the Claimant’s application for summary judgment, enforcing an adjudicator’s award and resulting in payment to the Claimant of over £140,000.00.

However, before deciding to do so, Cygnet challenged the enforcement on grounds that the adjudicator lacked the jurisdiction to make the decision he had and / or had breached the rules of natural justice.

By way of background, BDP was asked to undertake construction works for Cygnet in respect of its new hospital in Wolverhampton. The hospital was completed and BDP asked for payment of the retention sum (c.£170,000.00). Cygnet refused and instead requested payment of c£180,000.00 for alleged liquidated damages for late completion and defects. The dispute was referred to adjudication.

One of the arguments in the adjudication was the notice for liquidated damages issued by Cygnet was defective in that it contained the wrong amount for liquidated damages (ironically, BDP said it should be £14,500.00 per week, whilst Cygnet said it should be what it had stated; £1,000.00 per day). The adjudicator found that neither party had provided sufficient evidence on the point and so liquidated damages were not awarded. He went on to award the majority of the retention sum, less a figure for which further evidence was required.

Cygnet didn’t pay, and so BDP sought to enforce the decision in the High Court (TCC). The matter went before Mr Justice Constable, the Judge in charge of the TCC. Cygnet argued that there had been agreement between the parties that liquidated damages applied and that it was either £14,500.00 pw or £1,000.00 pd. The adjudicator therefore had to decide whether it was one or the other. It relied upon an analogy that the parties had said a building was either red or yellow, it was therefore the adjudicator’s job to decide which one. Cygnet argued it was not open to the adjudicator to conclude the building did not exist.

BDP disagreed and argued it was the opposite; neither party accepted the others as a secondary position, they rejected it. Further, using the same analogy, the adjudicator had not concluded the building did not exist, only that the evidence of its colour had not discharged the evidential burden by either party.

Mr Justice Constable found in favour of BDP; there was no agreement between the parties that it was either £14,500.00 pw or £1,000.00 pd (a binary option) limiting the adjudicator’s jurisdiction. Nor was the rejection of the evidence from both parties a decision in excess of his jurisdiction or a breach of natural justice. There had been no concluding that the building did not exist, only that the evidence didn’t support either party’s position on the point.

The case highlights the nuance between the parties agreeing a fact which an adjudicator cannot go behind on the one hand, and parties arguing a limited scope of outcomes for which the adjudicator is tasked with deciding, on the other.

The approved judgment is here.

Do you have a contentious construction matter which MD Law can help resolve? Call 0114 299 4890.

 

Can we help you?

For further information on MD Law call 0114 299 4890 or email info@mdlaw.co.uk. Alternatively, you can contact us using the button below:

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.